Village
delays Gaunt Pool opening
Two weeks behind its originally scheduled opening, the
opening of the Gaunt Park Pool has been delayed once again, and the public
pool may now open for the season early next week, Village officials said
this week.
Village officials placed blame for the latest delay on
King Painters & Sandblasters of Dayton, which was hired to paint the
pool. Normally two coats of paint would be applied to the pool, said Terry
Cox, the Village parks director. But the Village claims that King has
applied a coat of primer and only one coat of paint to the pool.
Because the Village was expecting King to apply one more
coat of paint on the pool last week, the Village had to delay the opening,
which had been rescheduled for June 7.
“We wanted
the job totally done and out of the way, but that’s not going to
happen right now,” he said.
Sherman King, the
owner of King Painters & Sandblasters, however, said that his company
has completed the project and that his company has applied two coats of
paint and one coat of primer to Gaunt Pool.
King said that the
pool’s black stripes, which designate the swimming lanes, were painted
on Sunday, May 25, and that the company was at the pool Monday, June 2,
doing touch-ups. King submitted a final bill to the Village the same day.
“We’re
satisfied that they’ve got a good job,” King said.
But the Village is
not satisfied with the final project. On Monday, Village Manager Rob Hillard
told Village Council that the “contractor hasn’t delivered.”
Both Hillard and Cox said on Tuesday that the Village had expected King
to apply a second coat of paint last week.
“I feel the
job should have been done” in time to open the pool on June 7, Cox
said.
Cox did say that
King has done an “excellent job” on the project, but that
the Village’s project has not been a priority for King Painters.
Sherman King indicated
that the spring weather made it difficult to finish the project, but he
said any blame belongs to the Village. For instance, the Village did a
sloppy job cutting the grass around the pool, he said, and did not clean
up grass clippings that then blew into the pool. “The delay has
definitely been on their part,” King said.
Village officials
have acknowledged that the weather delayed the opening.
In separate interviews,
both Cox and King accused the other of unprofessional behavior. Cox said
that King has given the Village “the run around” for the last
week. King said that Cox has been “badgering” him to complete
the project, even though King has said the pool is now painted.
The total project
cost is $13,000 and King has so far been paid about $9,500, Cox said.
Village Parks and
Recreation staff started filling the pool with water on Monday. It takes
several days to prepare the water in the pool for swimming. Cox estimated
the pool could open by next Tuesday, June 10, while Hillard said it would
be open by June 11.
Cox said that he
thinks the paint will fade by the end of the season. Another coat of paint
will be applied to the pool after it closes.
The Village plans
to keep the pool open an additional week in August.
The Village first
delayed the opening of the pool over the Memorial Day weekend after the
heavy spring rains and unexpected problems hampered King Painters’
efforts to paint the pool. In addition, King found soft spots in the walls
of the pool as the surface was being prepped for painting. The company
repaired the problems.
—Robert
Mihalek
|